—Selected projects
Measured at handover, not promised
Three facilities in three very different grid and climate conditions, with the density, PUE and programme each of them actually achieved.
—Selected projects
Delivered, measured, running
Representative projects across climates, grid conditions and densities. Figures are the measured values at handover, not design targets.

01Delivered
50 MW AI training campus
Arid inland site, dedicated 110 kV connection
EPC — three halls, own substation, dry-cooler field, DLC to every rack
IT load
50 MW
Racks
1,200
Density
80 kW
PUE
1.18
Tier
III
Programme
18 mo

02Delivered
8 MW urban colocation retrofit
Dense city block, two diverse fibre entries
Design & Build — structural strengthening, rooftop plant, 2N power train
IT load
8 MW
Racks
410
Density
20 kW
PUE
1.32
Tier
IV
Programme
14 mo

03Delivered
24 MW free-cooling HPC facility
Cold climate, hydro-fed grid connection
EPCM — long hall, air-side free cooling, immersion pilot block
IT load
24 MW
Racks
600
Density
40 kW
PUE
1.09
Tier
III
Programme
16 mo
Next step
Tell us what you are building
Send the site status, the grid offer and the target load. You get a concept, a power and cooling strategy and an indicative CAPEX back.